Swiss Grid Operations Meeting on 2022-10-13 at 14:00

*Next meeting: *



Minutes:

ATLAS:

ALPS back online in week 2

Running on Fort only, Gele remains as a test cluster

Several hiccups affecting Bern

CMS:

no major issue in the past month

LHCb:

no jobs sent for a few days - some workflows re-adjustments at cern - now back full as usual

Problems with the new ARC - asking for LDAP server, but it shouldn’t - debug on going

Riccardo
we should agree that LDAP is not used by anybody - to be discussed next Tuesday meeting

Miguel
do you want to roll back ? Contact Vladimir (if roll back he can’t debug)

CSCS:

move to Fort only / Shall we keep Gele open such that also CERN can do tests ?

LHCb can in principle run on ALPS too. As soon as the picture is clear (see LDAP) we will know better

Migration to ALPS

Daint out in 2023

Needed CEPH storage coming end of the month

months/weeks to deliver 100 nodes (48 nodes at the moment need 80 in total)

Ramp up until end of the year , still have a couple of months for final tuning

Because of scale up issues on ALPS, we may run longer than April on Daint

Possible power cuts from government to be expected

ATLAS

CMS

LHCb

T2 Sites reports

CSCS

UNIBE

  • Troubled month for compute both on LHEP and Ubelix
  • Completed integration of the Tier-2 pledged storage with the NDGF-T1

T3 Sites reports

PSI

UniGe

EGI / WLCG

  • Any news about the negotiations?
  • We should keep in mind that the fee structure is expected to change, so keeping not useful entries in GOCDB might increase the cost

Review of open tickets

https://ggus.eu/index.php?mode=ticket_search&supportunit=NGI_CH&status=open&timeframe=any&orderticketsby=REQUEST_ID&orderhow=desc&search_submit=GO


5 of 5 Tickets
Ticket-ID Type VO Site Priority Resp. Unit Status Last Update Subject Scope
158835   none UNIBE-LHEP less urgent NGI_CH in progress 2022-10-13 DPM migration and decommission ... EGI
158220   cms CSCS-LCG2 urgent NGI_CH in progress 2022-09-16 Submission using tokens to ARC ... WLCG
157362   none T3_CH_PSI very urgent NGI_CH assigned 2022-09-06 Enable SRR for WLCG dCache sites ... EGI
154102   dune UNIBE-LHEP less urgent NGI_CH on hold 2021-12-22 Local accounting for DUNE jobs at ... EGI
150373   dune UNIBE-LHEP less urgent NGI_CH on hold 2021-12-22 Enable DUNE queue for CPU and future ... EGI


  • Attendants
  • CSCS:
  • CMS:
  • ATLAS:
  • LHCb:
  • EGI: *

Topic attachments
I Attachment History Action Size Date Who Comment
PDFpdf ATLAST2Report-Sep2022.pdf r1 manage 2040.4 K 2022-10-13 - 11:22 GianfrancoSciacca ATLAS Tier-2 Report
PDFpdf cscs_lhcb_20221006.pdf r1 manage 525.4 K 2022-10-13 - 12:21 RolandBernet  

This topic: LCGTier2 > WebHome > MeetingsBoard > MeetingSwissGridOperations20221013
Topic revision: r4 - 2022-11-09 - MauroDonega
 
This site is powered by the TWiki collaboration platform Powered by Perl This site is powered by the TWiki collaboration platformCopyright © 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback