LHConCray Meeting on 2016-11-02
Agenda
- Ongoing tests status report
Attendants
- Gianfranco (ATLAS)
- Fabio, Christoph (CMS)
- Dino, Dario, Stefano, Nick, Miguel, Pablo (CSCS)
Minutes
- We are in a time-critical situation, where help from everyone is needed, since the testing machine will only be available until the end of the month (date not confirmed yet).
- For ATLAS running all HC jobs is a first priority. Currently only 3/6 of the tests run.
- For CMS there are other problems at Central Operations that need to be solved (that currently impact Phoenix). Jobs are running in Brisi since the weekend and results are promising.
- No input from LHCb (Wednesdays not good for Roland)
Action items
- Miguel to check on Gianfranco's input to try to understand where the problem is
- Miguel to lower the minimum memory requirements of jobs from 3 to 2 GB/core, now that the Shifter memory leak seems to be solved.
- Gianfranco to help Miguel debugging and check with the ATLAS HPC Working Group to see if there is some sort of technical forum where we can get help
- Fabio/Joosep to continue debugging problems with CMS
- Pablo to send a status/progress report in a week's time and check if another meeting is needed after that.