Prioritized TODO list for Phoenix until February 2017

In order to properly schedule the work derived from our last MeetingCHIPPCSCSFaceToFace20160901 meeting together with all the other activities, we need a complete list of all planned activities. Unplanned tasks (such as incidents) will always take precedence.

The list will be checked every two weeks, including new incidents that may arise.

Priority goes from top to bottom, together with the expected work for 1 person and the proposed deadline.

Ticket Task Duration Deadline Done
  Ask for HW offers for SNF funding request + derived analysis weeks 25 Oct  
  Resolve efficiency problems (with Scratch?) ? 10 Oct  
  Look at ARC + ATLAS queue configuration to undetstand what happened in April'16 with Scratch high utilization hours 10 Oct  
  Cross-check ATLAS and CMS efficiency plots with known issues and understand the differences days 10 Oct  
  Join all VOs and start familiarizing with their dashboards/logs days 31 Oct  
  Update the RoadMap wiki page hours 25 Oct  
  Create full CSCS+VOs monitoring dashboard (incl. Hackathon) weeks 31 Oct  
  Authentication on Kibana with Grid Certificates hours 31 Oct  
  Identify relevant A/R metrics (and others) for each VO and track them days 31 Oct  
  _________________ TASK REVIEW _________________      
23008 Discussion and implementation for VOBoxes weeks 30 Nov  
  Need to understand the impact of not imposing memory limits (e.g. swapping nodes?) hours Dec  
  DCACHE Update weeks Dec  
23515 SLURM reports are broken days Dec  
  Clean Monitoring on Wiki days Feb  
22368 Complete Nagios check with info from the VO and publish in Wiki days Feb  
  Puppetize cvmfs,argus days Feb  
  Foreman dismission hours Feb  
  Update Doc on wiki days Feb  
  Implement HA on Argus days Feb  
  Puppetize Storage infrastructure weeks Feb  
  Add per-VO walltime usage to accounting plots hours Feb  
24518 Check EGI accounting days Feb  
  Implement nodehealthcheck days Feb  
23114 Sudo rights on arc0[1,2,3] + arcbrisi days Feb  
  Finalize BDII lbcd->keepalive days Feb  

Monitoring Dashboard details

This section contains details about the common monitoring dashboard.

For all: please add two metrics that you would like to see in the Dashboard.

Readers' comments

 
Edit | Attach | Watch | Print version | History: r15 < r14 < r13 < r12 < r11 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r12 - 2016-10-19 - PabloFernandez
 