New (CSCS) storage system (4x Huawei OceanStore 6800 V5, aggr. W/bw ~40GB/s, 18.1PB) has been delivered and configured (will be used also for dCache)
Installing/configuring new 'se' nodes to start migrating data
Will then decommission old servers and move the ones still under warranty to the new island
Spctrum Scale
Finalizing the plan to:
Move from IB to 25G (need to replace card on each server) and re-configure GPFS
Move 16 servers from old island to new island
Move (SSD) storage from old island to new island
Attach new exp. units to sc9000 controllers (doing only SSD now) and move GPFS "slow tier" from DDN SFA12k to sc9000
Will need 2 days maintenance (but will do the best to make it in 1 day). Maintenance will be announced as soon as we have all things planned. Target dates are next week or the week after
Accounting numbers (from scheduler) from last month