Swiss WLCG Operations Meeting on 2012-01-12

Agenda

Status

  • CSCS (reports Pablo):
    • Entering Phase E
      • Computing Expansion. AMD CPUs on all 10 Dalco nodes were updated to Interlagos, increasing the cluster capacity by 252 HS06 and 80 job slots.
      • Storage Thumpers substitution. All Thumpers are empty and switched off. Replacement has also provided some extra space, rising our total to 1.11 PB (base10), or 557 TB per experiment.
      • Lustre to GPFS migration. Lustre is finally out of our system, leaving us with GPFS only. No software raids, two copies per file, metadata in SSD.
    • Next purchase: Phase F worker nodes for the new building

  • PSI (reports Fabio):
    • Xxx
  • UNIBE (reports Gianfranco):
    • Operation report
    • Update on transfer rate degradation from NDGF / ND cloud
  • UNIGE (reports Szymon):
    • Xxx
Other topics
  • Topic 1
AOB

Attendants

  • CSCS: Pablo
  • CMS:
  • ATLAS: Gianfranco
  • LHCb:
  • EGI:

Action items

  • Item1
Edit | Attach | Watch | Print version | History: r8 | r6 < r5 < r4 < r3 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r4 - 2011-12-20 - GianfrancoSciacca
 
  • Edit
  • Attach
This site is powered by the TWiki collaboration platform Powered by Perl This site is powered by the TWiki collaboration platformCopyright © 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback