Reducing queue closure time before scheduled downtimes

Right now we are closing the queues 2.5 days before scheduled downtimes. It turns out that this is too much.

There is a big difference between the required walltime specified in your VO cards and the time the jobs actually take to run.

In this table, we gathered the information specified in the VO cards, and the statistical information taken from the last 5 months. Only jobs longer than 1 hour are considered.

value lhcb atlas cms
CPUTIME in VO card ? 37.3 19.7
max CPUTIME in queue 32 48 24
PROPOSED CPUTIME in queue 32 42 24
WALLTIME in VO card 30.7 41.6 72
max WALLTIME defined in queue 48 48 72
PROPOSED WALLTIME defined in queue 48 42 72
max(avg,median) real job CPUTIME 21.8 3.5 3.5
max(avg,median) real job WALLTIME 25.8 4.9 5.5
95% of jobs finish below WALLTIME 48 19 20
PROPOSED closure time before downtime 48 20 20
(time specified in hours)

We should review the proposed closure time before downtime some time after changing the walltime defined in the lhcb queue, it will probably influence the statistics, since lhcb tried to use all the time it's given in the queue.

Also, please keep in mind that the walltime limit in the queue is the number that is published but it is relaxed. We give 6 additional hours of courtesy.

Readers' comments

 
Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions
Topic revision: r2 - 2010-10-26 - PabloFernandez
 
This site is powered by the TWiki collaboration platform Powered by Perl This site is powered by the TWiki collaboration platformCopyright © 2008-2024 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback